The village has decided that its next priority is to build another classroom building, allowing each grade to have its own room, and to establish a library.
The budget for the building is roughly $21,000 USD. As of September 14, 2025, 93% of the needed funds have been raised.
Funds Raised so far!
Third Building Reverse Timeline:
July 2025 to August 2025: Getting Close to Finishing the building
Supplies to finish the roof, install the doors and windows and plaster the walls arrive. Works starts on Doors and Windows.
Steel to install Doors and Windows
Steel for Window Coverings
Steel added to frames
Frames for Windows
Bars for Windows
Plaster supplies for the building
March 2025 to June 2025: Finish Wall, Start Roof
We have gone as far as we can until more funds are raised.
March 21, 2025: The walls are close to being finished.
April 29, 2025: Roof work has started
June 2025: Work pauses as we await more funding.
December 2024 to February 2025: Walls going up
January 15, 2025: Walls are going up! This picture shows how they first stack the bricks as high as they can standing on the ground, and then an on-site scaffolding is built to do the next layer.
February 3, 2025: They created a rebar tower in the corners to tie the walls and roof together. Notice how the brick extended into the corners
February 5, 2025: A form is built around the rebar tower. As you can see in the Feb 3rd picture, the bricks on the side are embedded in the concrete column. When all the vertical columns are done, horizontal columns are made the same way.
September to November 2024: Foundations being backfilled
We have gone as far as we can until more funds are raised.
Sept 27, 2024: Backfilling Foundation
Nov 6, 2024: Finishing the subfloor
Nov 6, 2024: Finishing the subfloor and preparing for the structural concrete columns.
August 2024: Construction has started!
Brick Foundations underway
Digging Foundation
Brick and Gravel in front of original building
July 2024: Supplies are arriving as funds become available
Brick Delivery
Supplies for construction
Delivery of Sand for concrete
Please contribute to help us build another classroom building so that each grade will have its own classroom and house the school’s growing library.